Friday, February 09, 2007

The Fluidity of Cyclical Cleansing

Final Goals

1/16” Site Model with complete intervention

1/4” Detail model of connection from Laundromat-Garden-Bath

1:1 Detail of a joint involving water

1/16” Site Plan

1/8” Plans of Laundromats, Bath and Garden

1/16” Site Sections

1/8” Section(s) of connection; Laundromat-Garden-Bath

Elevations

Hopefully perspective drawings or 3d renderings

Detailed Wall Sections

Detailed analysis of water treatment process

Statistical data supporting design;

1. Capacity of Water treatment

2. Dispersion Methods

3. Area Coverage

4. Some additional Calculations…(TBD)

Monday Feb. 12

-Reevaluate placement of Laundromats and construct a model of a further developed connection between Laundromat and bath. (More aggressive break of the ground plane)

-Continue to research and diagram grey water treatment. (May help inform connection between programs)

Thursday Feb. 15

-Finalize location of Laundromats

-Work on Public Bath in plan and Section (Consider further expansion
into east side of garden and start to develop connections between ground plane)

Monday Feb. 19

-Continue to develop overall scheme

-Start to choreograph path/sequence through garden and relationships to other 2 programs. (How does one enter? How are the senses engaged? How does the flow of water inform the path of the user and vice-versa? Answer additional questions…)

Thursday Feb. 22

-Develop a moment for the Pin-up that is a diagram of the project. (The connection between the programs and the involvement of water)

-Develop overall plans and sections for Pin-up

-In process model at 1/16”

Monday Feb. 26

-In class Pin-up

Thursday Mar. 1

-Review comments and criticism from pin-up

-Start data analysis

Monday Mar. 5

-Continue to work on scheme development

-Continue to work on individual programs

-Connections and joints

Thursday Mar. 8

-Continue all previously stated up until this point

-Finish items that have not been completed to date.

Monday Mar. 12 (Spring Break)

-Develop plans, sections and elevations for midterm

-Continue 1/16” Site model

-Start to develop preliminary wall sections and details

-Consider materials

Thursday Mar. 15 (Spring Break)

-Continue all previously stated for midterm

-Develop either 1/4” or 1:1 model

Monday Mar. 19

-Midterm

Thursday Mar. 22

-Review comments and criticism from midterm and respond

-Make adjustments to plan and section as necessary to finalize overall scheme

Monday Mar. 26

-Finalize plans of each individual program and their connection to each other formally and experientially

-Do drawing diagramming the flow of water

Thursday Mar. 29

-Develop 1/4” Detail model of 3 program connection

Monday Apr. 2

-Continue all previously stated up until this point

-Finish items that have not been completed to date.

Thursday Apr. 5

-In class Pin-up

Monday Apr. 9

-Review comments and criticism from review and respond

-Develop Wall sections

-Materials

Thursday Apr. 12

-1:1 Detail model

Monday Apr. 16- Friday Apr. 28

-Last Minute Decisions

-Work out final details of wall sections

-Decide of Materials

-Construct final models, drawings, etc.

This is a preliminary schedule, where I’m sure I have left some things out. Some things may take longer than others but the goal is to have what is stated in the beginning for the final review plus more hopefully. (If all goes well)