1/22
  • Record site onto CAD
  • Site model
  • Begun site analysis
1/25
  • From site analysis, construct force diagram model
  • Begun program analysis
1/29
  • Based on site and program analysis complete parti model
  • Beginnings of plans
2/1
  • Further development of parti model
  • Plans/Sections
  • Begin analysis of certain key moments for further development
2/5
  • Completion of all above with complete drawing/model, in larger scale, of key moments/details